The aircraft carrier USS John F. Kennedy left HII Newport News Shipbuilding on Wednesday for Navy acceptance trials, the shipbuilder said.
“These trials will test and evaluate important ship systems and components,” the shipyard said in an online statement. “We wish them a safe and successful time at sea.”
The trials are the last major evaluation before the Navy accepts Kennedy, the second Gerald R. Ford-class aircraft carrier. Neither the Navy nor the shipbuilder said how long the trials would last. The shipbuilder completed its initial sea trials in February.
Kennedy is scheduled to be commissioned in March 2027. The Congressional Research Service estimated last year that its final procurement cost will be just under $13.2 billion.
According to the Navy, design changes, along with problems involving the ship’s electromagnetic weapons elevators and arresting gear landing system, delayed delivery by 20 months, from July 2025 to March 2027.
The carrier was also retrofitted with Raytheon’s Enterprise Air Surveillance Radar, which the Navy said will improve air defense coordination and speed tracking of incoming threats. Congress required Kennedy to be capable of operating the F-35C Lightning II, the carrier-based version of the fighter jet also flown in other variants by the Air Force and Marine Corps.
Kennedy is expected to be homeported first at Naval Station Norfolk, Virginia, before moving to Naval Base Kitsap, Washington, in 2029.
After Kennedy is commissioned, work will continue on the next Ford-class carriers, USS Enterprise and USS Doris Miller. Enterprise is scheduled to be commissioned in July 2030, and Doris Miller in February 2032.
The Navy said in January 2025 that it planned to request two more carriers, to be named USS William J. Clinton and USS George W. Bush. The ships still require congressional approval and shipyard contracts.
The Navy plans to retire older Nimitz-class carriers as Ford-class carriers enter service. USS Nimitz, commissioned in 1975, was originally scheduled to retire in 2025, but that date moved to March 2027 after Kennedy’s delay. USS Dwight D. Eisenhower, commissioned in 1977, is now scheduled to retire no earlier than 2030, when Enterprise is expected to enter service.
The Navy’s long-range plan calls for 10 Ford-class carriers to replace all 10 Nimitz-class carriers.